Does anyone know where Primavera P6 stores the project start dates and the project finish dates in the database?
I tried to find this information in different tables, including but not limited to, Project, Task, ProjWBS, but it is not there.
Thanks in advance.
look in the TASK table for target_end_date / target_start_date. Here's documentation on the P6 db schema (for v8).https://docs.oracle.com/cd/E20686_01/helpmain.htm?toc.htm?schema_documentation.htm