I am reading a sheet in Excel and creating a Microsoft Project Plan of tasks, Work, Notes, etc.
The code is being executed out of MS Excel.
How can I get the Active.Project
to assign, SetTaskMode Manual:= False
?
I receive an error, please note Application.Visible = True
.
As far as .Application.Methods
(Project) go, I am able to invoke the Application.About
screen, i.e on Sub execution the MS Project About screen opens up, however after that line, it stops.
Basically, I would like to set the Active Sheet Task Mode to be set to 'automatically scheduled' as the default for all tasks as they are being imported.
The project property in question is NewTasksCreatedAsManual and is used like this to make all new tasks auto-scheduled:
ActiveProject.NewTasksCreatedAsManual = False
Alternatively, to set the task mode to auto-schedule on an individual task, use the Manual property like this:
tsk.Manual = False
' or to change to manually scheduled
tsk.Manual = True