We are a small team considering moving to TFS 2010 from Source Safe for richer ALM possibilities rather than just better version control. We intend to benefit from the work items, tasks, portal etc.
It seems to be that TFS 2010 is designed so that there is a one to one relationship between Team Projects and WSS Portal Sites. Is it somehow possible to have a single WSS Portal (v3.0 in my case) with multiple team projects pointing to it?
A well written book, namely "Professional ALM with VS2010 (Wrox 2010)", states on page 526 Chapter 22 that "As you can see, there is an option to point to an existing Web site instead of a new portal site". But the figure shows a different dialog page from an earlier beta possibly.
My concern is that, for a small team of less than 10 people like ours, a single Team Portal would be sufficent for the several projects active at any one time.
Should I go for a single {Team Project + WSS Project Portal} and use areas/iterations for the several different products? What are your relevant experiences?
That are just my 2 cents.