How to update TFS cumulative flow every day


In TFS 2017 Update 1 the cumulative flow chart is only updated every 7 days and looks like below. Is there any way to get it to update every day?

enter image description here


Solution

  • Even though the Cumulative Flow chart is marked with 7 days intervals it will be dynamically updated as and when you change the work item states.

    For example I have only one story active below out of 5 work items enter image description here

    Then I changed status of work items so that 1 is closed, 1 is new and other three active. The chart dynamically updates. enter image description here