I am using PSI interface of MS Project Server 2013 via Microsoft.SharePoint.Client context.
I need to get number or hours available for specific resource in specific date.
For example, Resource1 has current max units 100%. I set 8h work day, and it means that Resource1 has 8h every work day. I set Resource1 plan work 2h to today. So I need to get max avaliable hours for today: 8h - 2h = 6h.
//open project context
ProjectContext projContext;
projContext = new ProjectContext(pwaPath);
//load enterprise resource
projContext.Load(projContext.EnterpriseResources);
projContext.ExecuteQuery();
//get first resource
EnterpriseResource resource = projContext.EnterpriseResources[0];
//what should I do next?
Does exist any way to get this estimate without manual calculations?
DateTime dtStart = DateTime.Parse("09.04.2015");
DateTime dtEnd = DateTime.Parse("12.28.2016");
var plan = checkoutProj.GetResourcePlan(dtStart, dtEnd, TimeScale.Days);
projContext.Load(plan.Assignments);
projContext.ExecuteQuery();
DateTime dttest = DateTime.Parse("8.28.2016");
var assgn = plan.Assignments[0].Intervals.GetByStart(dttest);
projContext.Load(plan.Assignments[0].Intervals);
projContext.Load(plan.Assignments[1].Intervals);
projContext.Load(assgn);
projContext.ExecuteQuery();
assgn.Duration gives you workload for specific day.