I have a xml which, which has been created through net.sf.mpxj. in xml i have a milestone and a Task which are closed complete. when i import this xml to Microsoft project 2016, MileStone %Complete is changed back to 99%. For task i dont see any issue. its showing 100%
Few Observations: Actual Finish is showing N/A( from XML i am sending actual end date, not sure why its becoming N/A) % Work Complete is showing 0
Has anyone faced this issue before, if so could you please help me!.
Thanks in advance.
I had a quick look at this using your sample XML file. I tried various combinations of date, work, and duration attributes to get Project to report the percent complete correctly, but the only thing which worked for me was to supply an explicit percent complete value for the task. The only thing I can think is that Project is trying to calculate the percent complete value, but has a rounding error which means you never quite get to 100%.