Giving estimates for large scale projects in an Agile Environment


My firm just got its first large-scale development project inquiry and I would like to use an Agile process. The client has a vision for the application but openly admits to having very few requirements and recognizes that we will have to charge by the hour. Because of this, I've all but sold him on an Agile approach.

The problem is that he wants a figure to budget around. I've read a number of articles that pretty much advocate against giving up an estimate because the client will budget for that number and even as requirements change, the number in their head and in the books doesn't.

I've read there are a number of ways to factor in pricing in the contract, but almost all of them (save one) incorporate an up-front number. This just seems to violate the entire set of principles of Agile development.

So my question is, if you're an Agile shop, how do you manage to circumvent this Catch-22 of Agile development?


Solution

  • Here's the fundamental question.

    When will the client think they're done?

    If they think they'll be done by June, then you put an Agile team in place. That's 4-6 people for 6 months. That's the budget. Essentially, you do the multiplication for them. team * rate * 6 months.

    If they think they'll be mostly done by June, but there will be more work after that, then you're possibly looking at 9 months of work. Again, you're just doing a multiply that they could do for themselves. team * rate * 9 months.

    If they think that you'll be their development team for the foreseeable future, give them a price that will get the project through to the end of the year. team * rate * 12 months.

    Since each release is an opportunity to reprioritize, you should be pricing each release as as separate piece of work based on the things you will get done in that release. Since it's their priority scheme, they control what you build, they control the budget, phase by phase.

    Often your client really wants to know how much a particular feature set will cost. Instead of ask that, they ask about overall budget (which is silly). Spend a lot of time on the first release showing what they get and how much that first release will cost.

    Eventually, they'll see the fundamental truth.

    They're buying the features from most important to least important. If they prioritize correctly, they can stop spending money at any time and have something useful.

    Done is a relative term. Some projects are "done" because there's no more money. Others are done because there's no more time. Rarely (at least in software development) is a project ever done because we ran out of things to do.