How can we *set* deadlines, to allow us to work to them effectively, in an agile way?


I'm working in a team that's been consistently and fairly successfully working in an agile approach, and this has been working great for the current project until now, for our initial work, as we incrementally build the product.

We're now moving into the next phase of this though, and the management are keen for us to set some specific deadlines ourselves, for when we'll be in a position to demo and sell this to real customers, on the order of months.

We have a fairly well organised large backlog for each of the elements of functionality we'd like to include, and a good sense of the prioritisation of these individual bits of functionality.

The naive solution is to get the minimum list of stories that would provide a demo-able product, estimate all of those individually, and add them up and combine with our velocity to get a date, and announce we'll be demoing from then. That leaves no leeway though, and seems likely to result in a mad crunch as we get up to deadline time, which I desperately want to avoid.

As an improvement, I'd like to add in some ratio of more optional stories to act as either contingency or bonus improvements, depending on how we progress, but we don't have any idea what ratio would be sensible, or whether this is the standard approach.

I'm also concerned by having to estimate the whole of our backlog all in one go up-front, as that seems very time consuming, and it seems likely that we'll discover more information in the months before we get to that story, which will affect our estimates.

Are there recommended approaches to dealing with setting deadlines to allow for an agile development process? Most of the information I've seen seems to be around handling the situation once you've got a fixed deadline to hit instead. I'd also be interested in any relevant literature or interesting blog posts that cover this issue.


Solution

  • Regarding literature: the best book I know regarding the estimation in software is "Software Estimation: Demystifying the Black Art" by Steve McConnel. It covers your case. Plus, it describes the difference between estimation and commitment (set-deadline, in other words) and explains how to derive the second from the first reliably.