I"m working with flow job scheduling issue. is there a mathematical equation to compute the fitness instead of the Gantt Chart ? thanks in advance.
It seems the most common fitness measure would be the make span. Specifically you would be minimizing the total length of the schedule (Smaller make-span --> better fitness).