How do we deal with prototyping in Scrum?


We are new to Scrum and part way through the first sprint we have realised that one of the team members (a developer) needs to do some investigation into how navigation should work (from a user perspective) in the application.

So at the end of this investigation we should have a proposal or prototype of how something should work. But it wont have been actually coded in the application.

So my question is, how should we deal with something like this in terms of the sprint planning. I don't really see it as being user story, but what is it, and how is it treated in Scrum? Does something need to be added to the planning board for the investigation?

Thanks

Paul.


Solution

  • Try to treat prototyping like any other requirement as much as possible. Think about what you want to achieve, create a user story, define one ore several tasks and estimate them during sprint planning. Think of the development team being the user in this case. Definitely have it on the planning board and track progress in daily Scrum meetings. If you have problems estimating the tasks, define them as "time-boxed", i.e. with the fixed time budget, to prevent "endless" work without results.